Construction Project 2011-2013

Eden Prairie Campus Construction outside
Construction Rendering

JANUARY 2012 UPDATE
The General Contractor and major subcontractors such as the mechanical (HVAC, plumbing, fire sprinkler) and electrical have mobilized on site.

Inside the college, temporary partitions have been built to separate construction traffic from campus activities.

Small view windows have been installed in the partitions so anyone can keep an eye on the construction progress.

Exterior fencing has been placed to designate the contractor staging area (dumpsters, deliveries, construction materials) as well as the designated areas for exterior demolition and construction.

Safety and directional signs are being installed and will be updated and modified as appropriate

Demolition is about 50% complete

SEE DEMOLITION PHOTOS


CONSTRUCTION AND RENOVATION OVERVIEW
The Hennepin Technical College Construction Project 2011-2013 includes remodeling of existing spaces at both the Brooklyn Park and Eden Prairie campuses. The Project will consolidate services for students into one central location and improve the physical spaces for the library and academic support services. The scope also includes a relocated main entrance, related site improvements along with updated mechanical and electrical systems. The overall design concept for the project mirrors recent college remodel projects by adding extensive glass walls and dramatically improving the amount of transparency and daylight.

The Project includes the renovation of approximately 37,880 square feet as well as an addition 2,300 square feet at the main entrance area to each campus. The Project will be executed simultaneously at each campus, in 3 Phases, spread over about 18 months.


 

     construction logo

    FLOORPLANS & RENDERINGS

    DATES & TIMELINES

    BEFORE, DURING & AFTER PHOTOS


    NOTICE: The Bookstores have moved
    BPC Bookstore: H160
    EPC Bookstore: E152


    OTHER CONSTRUCTION AND RENOVATION PROJECTS

    Boiler Replacement
    Area Mechanical will be replacing the Eden Prairie Campus boiler at a cost of $1,479,000.
    Construction began December 13, 2011
    Substantial Completion - May 15, 2012
    Project Completion - June 15, 2012


    CONTACT
    Please contact the following individuals is you have any questions:

    Safety Issues
    Erin Lynne 763-488-2506 or
    763-238-5536 (cell)

    Security Issues
    Randy Roehrick 952-995-1525 or 763-238-0905 (cell)

    Other Construction Issues
    Diane Paulson 763-488-2518 or 763-238-1355 (cell)

    Employee Concerns
    Sharon Mohr 763-488-2525 or
    763-238-9592 (cell)
     




Last updated by jlaabs : 2012-01-23 15:02:38